PROJECT 7:

OPTIMUM QUALITY WITH MINIMUM MANUFACTURING COSTS

 

Increasing

Standards

a

Determining raw material costs before through raw material selection by Fiber Mix Selection pc-program and then minimizing

2

b

Make Control Plan for new raw material process

3

c

Minimizing new raw material process cost by Technical Data/Machine Settings

3

d

Maximizing profit by Linear programming

3

7.1  Select Raw Material with Fiber Mix Selection Pc-Program

Different cotton will be brought all over world. And they are examined to make yarn. Existing production costs are compared these raw material production costs. Raw material will be selected suitable. To test to minimize production costs. Obtained quality criterions values introduce what do for reduce raw material cost through compare existing blend.

7.2  Prepare Control Plan for Raw Material Process and Implementing

After selecting suitable raw material, necessary control plans are prepared for their process. Then fiber values, yarn quality values and performance are compared between their harmonies while implementing experiment production. And costs are compared from priority costs.

7.3  Technical Data /Machine Settings

7.4  Minimize costs and Maximize Profitably with Linear Program

It is not only enough to reduce costs, improve quality, put new innovation production on the market before your rivals on the international market competition. Separately production plan must be prepared through determine which products are profitable in the mill. In this scope linear programming has important function. In this project linear programming does

 

Knowledge Based Quality Systems             Proses Optimization and R&D Projects for Textile Mills